SITE LOADING
February 2022 Work Progress

February 2022 Work Progress

Watering rolling the raft footing area of crusher plant and placing the footing mat on it

Excavator removing loose soil in phase 3

Marking given for plinth beams for entry portal arch.

gravel filling to 40 feet road for levelling at phase 3

Received crusher plant material to site.

Sloping the 60 feet road is in progress at phase 3