A Digital platform to view Pragna Hill County work progress and developments
-
December Developments
approach CC Road work 16th Dec 2022 cc road on approach road 12th Dec 2022 Compressor blasting done on hill area Excavator shifting blasted material and loading dumpers in phase 3
-
November Development Updates
Excavators loading dumpers in phase 3 Excavator levelling 100′ & 30′ road in phase 3 Road Leveling work Rig placing holes in phase 1 and phase 3
-
August Updates
Underground Drainage and electricity works PHC Drainage & Electricity PHC Drainage & Electricity PHC Drainage & Electricity PHC Drainage & Electricity 60 FT CC Road works 60′ FT CC Roads Work 60′ FT CC Roads Work 60′ FT CC Roads Work 60′ FT CC Roads Work Loading the gravel and filling in 60 and 100 […]
-
July Developments Update
Road Formation Road Formation Road Formation Road progress Crusher Plant Crusher Plant Crusher Plant Crusher Plant Crusher Plant Crusher Plant Under Ground Drainage Underground Drainage Underground Drainage Underground Drainage Underground Drainage Underground Drainage Underground Drainage Development Work Progress Plot Leveling Work Progress Venture Mapping Hoarding Hoarding Hoarding Hoarding Work Progress Land Leveling
-
June Developments Update
Excavator clearing soil on sheet rock in phase 3 on hill top. Excavator clearing phase 3 on hill top. Excavator clearing phase 3 on hill top. Excavator clearing phase 3 on hill top. Excavator clearing phase 3 on hill top. Dumpers unloading material at 2nd ring road of 100′ road in phase 3. Phase 3 […]
-
May Developments Updates
60′ Road Formation 60’ft Road 60’ft Road 60’ft Road 60’ft Road Crusher plant erection work is in progress Crusher plant erection Crusher plant erection Crusher plant erection Crusher plant erection Crusher plant erection Crusher plant erection Crusher plant erection Watering and rolling on roads at phase 3… Roads progress at Phase 3 Roads progress at […]
-
April Development Updates
Levelling the 60 feet road at phase 3. Previous Next Concreting completed for middle beams of crusher plant Previous Next Dozing the blasted material is in progress at phase 3 Previous Next Watering on 60 feet road at phase 2 Previous Next Crusher plant erection work is in progress. Previous Next
-
February 2022 Work Progress
Watering rolling the raft footing area of crusher plant and placing the footing mat on it Previous Next Excavator removing loose soil in phase 3 Previous Next Marking given for plinth beams for entry portal arch. Previous Next gravel filling to 40 feet road for levelling at phase 3 Previous Next Received crusher plant material […]
-
November 2021 Work Progress
Work at Hill CountyWork going on day and night, removing the boulders at 60 and 40 feet road and filling into the 100 feet road…At phase 3 giving uniform slope to the another approach road to the phase 3, removing the gravel and storing at stock point at phase 3. https://www.youtube.com/watch?v=Z-8P4mLjnQQ&feature=youtu.be