June Developments Update
Excavator clearing soil on sheet rock in phase 3 on hill top. Excavator clearing phase 3 on hill top....
Excavator clearing soil on sheet rock in phase 3 on hill top. Excavator clearing phase 3 on hill top....
Watering rolling the raft footing area of crusher plant and placing the footing mat on...
Work at Hill CountyWork going on day and night, removing the boulders at 60 and 40 feet road and filling into the 100 feet road…At phase 3 giving uniform slope to the another approach road...
Phase 3 leveling work going on and 100 feet road leveling, rock blasting and leveling of the...
Phase 3 leveling work going on and 100 feet road leveling along with 60 feet road leveling along with nod connections of...
Phase 1 site leveling progress work in March 2021, complete 22 acres is brought under site leveling progress as per layout...
Site leveling work progress is done in 22 acres which is phase...